November 14 → December 30 2022
Begin Public Process
December 30 2022
Complete Public Process
January 01 → March 01 2023
Preliminary Design
March 01 2023
Approvals Complete
March 01 → June 15 2023
Final Design
June 15 2023
Plans available to bidders
July 15 2023
Bids due to Town of Vail
August 01 2023
TC Contract Award
September 05 2023
Begin Phase 1 Construction
November 17 2023
End Phase 1 Construction
May 03 2024
Begin Phase 2 Construction
June 28 2024
End Phase 2 Construction - Project Complete